Published on January 3, 2024

SUMMARY

Streetscape Improvements along Pratt Avenue between Grayson Street to Maysville Road consisting of curb and gutter, parallel parking, sidewalks and landscape medians. Street resurfacing along Pratt Avenue between Russell Street and Grayson Street.


STATUS

Construction contract was awarded to Grayson Carter in January 2024 with construction anticipated to start in April 2024. Project is anticipated to take six months to complete depending upon weather and utility conflicts.

Updated April 11, 2024


COST & FUNDING

Total Cost: $1 million (estimated)

Contractor: Grayson Carter & Son Contracting Inc.


PROJECT MAP

A map showing planned streetscape improvements on Pratt Avenue in Huntsville.

Updated April 11, 2024

HSV Connect

Report a problem or submit a service request using Huntsville Connect

Get Started