Roadway Improvement Projects
On May 11, 2023, City Council authorized Mayor Tommy Battle to enter into an agreement with low bidder Grayson Carter & Son Contracting Inc. Because the affected portion of Monroe Road will be closed for construction for about four months, a detour will redirect motorists to Patterson Lane. Construction is underway and utility relocations are ongoing.
Updated July 21, 2023
Weather permitting, one lane of Governors Drive (adjacent to the median) from Memorial Parkway to Clinton Avenue will be temporarily closed from 9:30 a.m. to 3:30 p.m. each day for road and landscaping improvements. This project is estimated to continue through the end of September.
Two lanes of Governors Drive will always remain open. Traffic control devices will be in place to assist motorists. Please reduce speed and use caution in the work area.
July 21, 2023
Plans are complete, and the City is currently working on right-of-way acquisition for the remainder of properties needed.
Updated July 20, 2023
Environmental studies and site assessments are continuing. Public Involvement meeting is anticipated for early 2024.
Updated July 20, 2023
The road is complete to Mooresville Road. Phase 4B (west of Mooresville Road to Huntsville-Browns Ferry Road) is complete. This phase was opened to traffic on June 1. The fifth and final phase (widening Huntsville-Browns Ferry Road to I-65) is under construction and is approximately 90% complete.
Updated July 21, 2023
All work is complete and all lanes are now open. All the ALDOT requirements have been met and the project has been closed.
Updated July 21, 2023
The City is responsible for the next phase of construction on Winchester Road. This phase contains 2.25 miles of new five-lane roadway to connect to the recently completed portion constructed by the County. The right-of-way acquisition is scheduled to be completed by the end of December 2023. Construction is estimated to begin June 2024, pending utility relocations.
Updated July 21, 2023
Design is approximately 95% complete. The right-of-way acquisition is complete. Funding for utility relocations was authorized by ALDOT in June 2020. Each utility company will be responsible for designing and performing relocations in conflict with the roadway project.
Roadway construction will start upon the completion of sewer, electrical, fiber and gas relocations. Madison Sewer has relocated a sewer line on the south side of the road. Electric and communication line relocation is ongoing, and gas relocations have been bid and are slated to begin soon.
Other utility relocations (water and COH sanitary sewer) are anticipated to be included in the roadway project scope. The roadway construction will be performed with a detour route in place for motorists to use Trademark Drive to maintain two-way traffic during construction, which is anticipated to begin fall 2023. This roadway construction project duration is estimated to be 18 months.
Updated July 21, 2023
The project is substantially complete, and all lanes are open to traffic. Punch-list work is ongoing.
Updated July 21, 2023
The Research Park Boulevard construction is complete, and all lanes of traffic were opened on Sept. 29, 2022. Construction crews continue to complete the punch list items for project closeout.
Updated July 21, 2023