Roadway Improvement Projects
The roadway construction contract was signed by ALDOT in September 2023. The contract was awarded to the low bidder, Rogers Group Inc. The bridge work is completed, and the east side of the project was reopened to traffic in May 2026. Crews continue to work landscaping behind the curbs from Old Jim Williams to Wall Triana and finish the final paving surface shortly thereafter with striping and signage to complete the entire east side. Contractor has moved to the west side of Wall Triana and will be upgrading the existing railroad crossing to accommodate the new roadway. Remaining work on the west side will require additional lane shifts and road closures to complete all roadwork between Wall Triana Highway and Laracy Drive. Anticipated completion for the entire project is late 2026, with weather permitting.
Updated Aug. 11, 2026
The City of Huntsville awarded a contract to Wiregrass Construction Company on Nov. 2, 2023, to construct the Northern Bypass. Construction began in mid-November 2023. This project includes 1 mile of road improvements along U.S. 231 (Memorial Parkway) to accommodate the new intersection. Traffic was shifted to the new intersection in July of 2025, and a section of the new road was opened to traffic, between Memorial Parkway and Derwent Lane, in December 2025. Progress on the project has slowed as the contractor works through difficult site conditions at the west end of the project near Northgate Drive. Construction is approximately 70% complete with approximately 100 working days remaining on the contract duration, which is dependent upon weather and site conditions as work progresses.
Updated Aug. 10, 2026
Preliminary engineering and design are 75% complete. A public involvement meeting was held in January 2022. ALDOT is completing design. ROW is anticipated to begin in 2025 with construction scheduled for 2026.
Updated Feb. 21, 2025
The City and ALDOT are working to secure additional funding as the design proceeds. The project will be constructed in phases, with the first phased being near Providence Main. Right of way acquisition is expected to begin in 2025 with construction anticipated in phases from 2026-2029.
Updated Feb. 21, 2025
Contractor Rogers Group started work in 2023. The contractor shifted all traffic to the substantially-completed service roads in late 2024 and began construction of the new mainline and overpass at Mastin Lake Road.
The project is anticipated to take more than three years to complete. Motorists should expect delays and drive with caution in the 2-mile work zone.
Updated Feb. 21, 2025