South Parkway at Martin Road, Byrd Spring and Lily Flagg

Published on

SUMMARY

The project includes frontage roads and mainline construction, along with new overpasses intersecting Lily Flagg Road and Byrd Spring Road. The Martin Road intersection/bridge has expanded to include an intersection with traffic signals.

These projects will complete the remaining planned overpasses for the South Parkway and is managed by the Alabama Department of Transportation (ALDOT).


STATUS

Overpasses and frontage roads are complete and open.

Updated March 5, 2021


COST & FUNDING

Cost: $60 million

Source of Funding: Local & State – Alabama Department of Transportation (ALDOT)

Contractor: Reed Contracting Services, Inc.

This is a Restore Our Roads project.


Updated March 5, 2021