Meek Greenway between Sparkman Drive and A&M Campus
Published on
SUMMARY
This greenway consists of approximately 1.25 miles of new greenway between A&M and Sparkman Drive, consisting of a 12-foot wide paved multiuse path along the west side of Normal Branch.
STATUS
Major items of work have been completed. Ribbon cutting ceremony was held in November 2026. Contractor currently performing punch list times and clean up work.
Updated Aug. 10. 2026
COST & FUNDING
Estimated cost: approximately $2M for this new multiuse pathway.
Source of funding: This is a city of Huntsville Project
Updated Feb. 4, 2025