Published on January 3, 2024

SUMMARY

Improvements along Old Gurley Road consisting of approximately 2,550 lane feet and approximately 1,600 lane feet of Mountain Vista Way, just east of Moores Mill Road, to minimize congestion in the area. Work consists of intersection and road modifications to include curb and gutter, drainage and utilities to improve safety and access in the area.


STATUS

Work is about 98% complete, and the roads are now officially open.  Remaining work includes permanent striping, finalizing lighting, sod, and cleanup

Updated May 2, 2025


COST & FUNDING

Total Cost: $4 million (estimated)

Contractor: Rogers Group


PROJECT MAP

A map showing improvements to Old Gurley Road, just east of Moores Mill Road.

Updated Feb. 4, 2025

HSV Connect

Report a problem or submit a service request using Huntsville Connect

Get Started