Old Gurley Road Improvements
Published on January 3, 2024
SUMMARY
Improvements along Old Gurley Road consisting of approximately 2,550 lane feet and approximately 1,600 lane feet of Mountain Vista Way, just east of Moores Mill Road, to minimize congestion in the area. Work consists of intersection and road modifications to include curb and gutter, drainage and utilities to improve safety and access in the area.
STATUS
Work is about 98% complete, and the roads are now officially open. Remaining work includes permanent striping, finalizing lighting, sod, and cleanup
Updated May 2, 2025
COST & FUNDING
Total Cost: $4 million (estimated)
Contractor: Rogers Group
PROJECT MAP
Updated Feb. 4, 2025