SUMMARY

County Line Road will be widened to a five-lane road beginning at the city limits for approximately 0.35 miles through the intersection of Highway 72. This project will include adding a through lane in each direction along US Highway 72 from Hatcher Road to Crutcher Drive for approximately 0.4 miles and a west to southbound turn lane from Highway 72 to County Line Road. A north to westbound turn lane will be added on County Line Road.


STATUS

Roadway is complete.

Updated February 18, 2020


COST & FUNDING

Cost: $5 million

Source of Funding: Local & State – Alabama Department of Transportation (ALDOT)

Contractor: Reed Contracting Services, Inc.

This is a Restore Our Roads project.