Cecil Ashburn Drive

Posted on April 24, 2017

SUMMARY

This 3.4-mile project will widen Cecil Ashburn Drive, from two to four lanes between Old Big Cove Road and Four Mile Post Road, to improve traffic flow and incorporate safety improvements. The project includes eight-foot shoulders along each side of the roadway.


STATUS

There have been 81 days of work on the project and although there have been significant wet and cold weather events since January, the contractor continues to make progress on-site with very few days off. The contractor currently has 39 pieces of drilling and excavation equipment on site with ten additional dump trucks to relocate excess material.

Clearing operations are complete and blasting operations are approximately 80% complete. The contractor is approximately 60% complete with the storm drainage installation and is coordinating with multiple utility companies to begin relocation efforts. To date, Huntsville Utilities has completed electrical relocation and others are scheduled to begin their work next month.

The contractor will also begin installation of the new water line next month in an effort to complete all utility work and will begin to construct the new roadway subgrade shortly thereafter.

The project is expected to be fully complete by May 2020. The contractor is currently on schedule to restore two-way travel on the roadway by October 2019. Project completion is anticipated to extend an additional 8-10 months.

Updated March 28, 2019


COST & FUNDING 

Total cost: $18 million

Source of Funding: Local & State – Alabama Department of Transportation (ALDOT)

Contractor: Carcel & G

This is a Restore Our Roads project.


PROJECT GALLERY

Blasting Video

 


COMMUTER TIPS

Learn about alternate routes, safety, ride-sharing, and how to stay updated on the status of the project.


COMMUTER INFORMATION

Download and/or print the Cecil Ashburn Info page or the Cecil Ashburn Drive Presentation.


Questions?

E-mail: CecilQuestions@HuntsvilleAL.gov
Phone: (256) 427-5100


Recent News

Cecil Ashburn Drive Road Improvement Project set to begin Jan. 7

Road will close for 10 months to expedite construction and minimize disruption for motorists

The City of Huntsville is set to begin critical roadwork in early January to improve safety and increase ...

Read More

Public Meeting Sept. 13 on Cecil Ashburn Drive Improvements

The City of Huntsville and the Alabama Department of Transportation (ALDOT) are inviting citizens to learn more about planned roadway improvements to Cecil Ashburn Drive at a Public Involvement Meeting ...

Read More


PROJECT HISTORY

Read more about the Cecil Ashburn Improvement project.

Cecil Ashburn Drive Improvements

Aerial view of the route of the four-lane widening project for Cecil Ashburn Drive


Updated March 28, 2019