Roadway Improvement Projects
The work is anticipated to start in late 2026 and be complete within 60 calendar days.
View the ALDOT Public Input webpage to provide public comment on the project before Tuesday, Aug. 31, 2026.
Updated on Aug. 10, 2026
Design is complete, though awaiting permitting by the U.S. Army Corps of Engineers before work begins. Construction is anticipated to start mid-2025.
Updated April 11, 2024
Updated Feb. 5, 2025
A corridor study is now underway. Environmental Document has been completed. Funding has been allocated for design of Phase 1 to begin. Phase 1 consists of improvements on the south side of Interstate 565 with a direct connection from Madison Boulevard to Redstone Gateway. This will also lengthen the weaving distance between Research Park Boulevard (SR 255) and Madison Boulevard along Interstate 565. Redstone Arsenal will be providing the land needed to construct the improvements. We anticipate construction to begin in late 2027.
Updated Aug. 10, 2026
Currently in the corridor study phase. A public involvement meeting was held in August 2022. The city is currently working with Redstone Arsenal to define an alignment in coordination with all adjacent property owners.
Updated Aug. 10, 2026
Work is progressing and should be completed by August 28, 2026.
Updated Aug. 10. 2026
The site has been cleared, and construction on three of the four bridge culverts and gas, water, sewer, electric and communication relocations are complete. Construction of permanent signal at the new intersection of Bypass and Memorial Pkwy. should be active by end of Aug. 2025,
Updated Aug. 8, 2025
The City remains in right-of-way acquisition for the next phase of construction on Winchester Road. This phase contains 2.25 miles of new five-lane roadway to connect to the recently completed portion. The right-of-way acquisition schedule continues to change due to new development/ownership along this county growth corridor. Any changes to properties within this area require new legal descriptions, appraisals and offers to be made to each property owner to include active condemnation proceedings. Acquisition is anticipated to be complete by early 2027. Utility agreements have been approved by ALDOT for each utility provider to relocate upon completion of acquisition, and road construction will start immediately after. The road project is anticipated to take 18-24 months to complete construction. Once complete, Winchester Road will be five lanes for approximately nine (9) miles from Pulaski Pike to Bell Factory Road.
Updated Aug. 10, 2026
The roadway construction contract was signed by ALDOT in September 2023. The contract was awarded to the low bidder, Rogers Group Inc. The bridge work is completed, and the east side of the project was reopened to traffic in May 2026. Crews continue to work landscaping behind the curbs from Old Jim Williams to Wall Triana and finish the final paving surface shortly thereafter with striping and signage to complete the entire east side. Contractor has moved to the west side of Wall Triana and will be upgrading the existing railroad crossing to accommodate the new roadway. Remaining work on the west side will require additional lane shifts and road closures to complete all roadwork between Wall Triana Highway and Laracy Drive. Anticipated completion for the entire project is late 2026, with weather permitting.
Updated Aug. 11, 2026
The City of Huntsville awarded a contract to Wiregrass Construction Company on Nov. 2, 2023, to construct the Northern Bypass. Construction began in mid-November 2023. This project includes 1 mile of road improvements along U.S. 231 (Memorial Parkway) to accommodate the new intersection. Traffic was shifted to the new intersection in July of 2025, and a section of the new road was opened to traffic, between Memorial Parkway and Derwent Lane, in December 2025. Progress on the project has slowed as the contractor works through difficult site conditions at the west end of the project near Northgate Drive. Construction is approximately 70% complete with approximately 100 working days remaining on the contract duration, which is dependent upon weather and site conditions as work progresses.
Updated Aug. 10, 2026
Preliminary engineering and design are 75% complete. A public involvement meeting was held in January 2022. ALDOT is completing design. ROW is anticipated to begin in 2025 with construction scheduled for 2026.
Updated Feb. 21, 2025