Big Spring Park expansion to impact traffic on Church Street

Published on

As work progresses on the expansion of Big Spring Park at the site of the former City Hall, improvements to Church Street between Clinton and Williams avenues will begin next week and continue throughout the summer.

The Church Street upgrades will enhance pedestrian safety, construct streetscape features and better integrate the east and west sides of Big Spring Park – including a new crosswalk across the roadway.

The ongoing park expansion is refashioning the 2.4 acres on the east side of the road as a dynamic greenspace bringing new amenities to Big Spring Park.

Church Street Construction Timeline (weather permitting)

  • Tuesday, May 26: Church Street lane closures will begin with the northbound outside lane being affected for removal and replacement of the sidewalk. The lane is expected to reopen on Tuesday, June 23.
  • Tuesday, June 23: The median will close from Huntsville Utilities to Williams Avenue as work begins on building a tree-lined median on Church Street. The work is expected to be completed by Friday, July 10.
  • Friday, July 10: The two northbound lanes will close and northbound and southbound traffic will continue with single lanes utilizing the two southbound lanes. The lanes are expected to reopen on Wednesday, July 29.
  • Wednesday, July 29: The two southbound lanes will close and northbound and southbound traffic will continue with single lanes utilizing the two northbound lanes. The lanes are expected to reopen on Friday, Aug. 14.

Drivers are encouraged to use caution in the area and seek alternate routes, if possible, during the improvements.

Work on the expanded Big Spring Park – which includes a multi-level terrace plaza, improved ADA access and a pavilion for hosting community events as well as the Church Street improvements – is expected to be completed by the end of the year.